The Tuck's Point Rotunda Gets New Footing This Winter. Here's What Changes on Manchester's Harbor

This spring, Manchester-by-the-Sea voters agreed to pay for keeping the Tuck's Point Rotunda where it has stood since 1896. Starting this late fall, that decision becomes a construction season. Over the off-season, a contractor will replace everything under the Rotunda and put it on steel pilings. When it's done, the Rotunda should look almost the same, just five feet higher.

Built in 1896, Standing on 1970s Timber

The Rotunda dates to 1896 and was designed by Boston architect E.A.P. Luscomb. In a March 2026 update from the Town Administrator's office, the Town calls it "the Town's cherished version of motif #1," a subject that keeps turning up in artwork and photographs.

The part people photograph is old. The part holding it up is newer, but it's wearing out. The timber support pilings were last replaced in the 1970s, and timber pilings last about 50 years. A condition assessment in 2020 found the support structure compromised by age, weather and rising sea levels. In the same update, the Town says its concern is the growing number and severity of winter storms, and that it wants the work finished "before any significant damage occurs."

Option 1 Rebuilds Everything Below the Floor

The Town didn't start with one plan. In 2022 it hired the engineering firm Foth, using a $60,000 grant, to develop alternatives for rebuilding the supports. The Select Board reviewed four options in June 2023 and held two public forums. On September 18, 2023, it voted for Option 1.

Moving the Rotunda was part of the debate. In August 2023, before the vote, The Manchester Cricket ran a letter arguing that the Rotunda would be better on land. The letter listed the moments it has hosted over the years, including picnics, weddings, prom photos and memorials. The Town chose to leave it in the water.

Here is what Option 1 does:

  • Keeps the Rotunda in its current location and on its current footprint
  • Raises it from 14 feet to 19 feet above mean low water
  • Replaces the undercarriage and swaps the timber pilings for steel
  • Makes the pier ADA compliant while keeping the Rotunda's historic appearance

Nearly all of the spending goes into parts nobody photographs. The structure above the floor stays the same. The changes are in what holds it up and how high it sits.

The State Said No, and the Town Paid Anyway

The Town's estimate in March was $3.6 million. Voters at the 2025 Annual Town Meeting had already put in $1.3 million, with $800,000 from the general fund and $500,000 from Community Preservation funds. In 2025 the Town also applied for a $2.5 million Seaport Economic Council grant and a $425,000 Coastal Zone Management grant. Neither came through.

That left a gap. The Town asked for $350,000 more in Community Preservation money plus a $2 million debt exclusion on a 20-year bond. The Town estimated the tax impact at $42 per $1 million of property value. The request needed two approvals, first at Town Meeting and then at the ballot box. It got both.

Vote Date Result
Article 14, Rotunda borrowing, Annual Town Meeting April 27, 2026 Passed 140 to 72
Article 19, $350,000 CPC restoration allocation April 27, 2026 Passed 162 to 8
Question 7, $2 million borrowing authorization May 19, 2026 Passed 319 to 121
Question 8, Proposition 2½ debt exclusion May 19, 2026 Passed 294 to 135

Compare those margins with harbor dredging, which was on the same ballot. Dredging's borrowing question passed 367 to 77 and its debt exclusion passed 342 to 99. The Rotunda drew more opposition than dredging. Even so, roughly two out of three votes cast on its debt exclusion were in favor. The official May 19 election results and the Annual Town Meeting minutes have the full counts.

A Bid Under the Estimate, and a Winter of Work

Bids opened September 23. According to the DPW fall update dated October 12, BTT Marine Construction was the apparent low bidder at about $3.28 million for the Tuck's Point pier and Rotunda. That's below the $3.6 million estimate from March. The Town said it was in the process of awarding the contract.

That same bid covers more of the harbor than Tuck's Point:

  • Reed Park floats and Morss Pier: about $1.27 million, with completion expected by late May 2027
  • Tuck's Point pier and Rotunda: about $3.28 million, with completion expected by early September 2027
  • Harbor dredging: priced for the 2027–28 dredging season, which runs October through February. The Town will set the final cost and timeline once an anticipated grant becomes available in summer 2027.

The Reed Park work is a dock expansion. It is funded by a $600,000 Boater Infrastructure Grant and a $568,250 Seaport Economic Council grant. Morss Pier has its own $452,000 Seaport Economic Council grant. The Town's March update said bundling the harbor projects "could provide for efficiencies that would result in significant time and cost savings."

The Town expects harbor construction to start in late fall and continue through spring. The October update gives no specific start date. For news about the work schedule at Tuck's Point, check the DPW and the Town's website. The DPW office number is 978-526-1242.

Another winter project is driven by the same rising water, a few blocks inland. On Tappan Street, N. Granese & Sons is replacing a 120-year-old cast-iron water main and a deteriorated sewer main. The firm is also rebuilding the drain system with a tide-control valve and stormwater treatment. Work starts this fall and continues through the winter as weather allows. Sidewalks, curbing, street lighting and final paving follow in 2027. Between Tuck's Point and Tappan Street, this winter's public works are mostly about tides.

The Chowder House Calendar Is Already Open

People often lump the Rotunda and the Chowder House together, but the Town treats them separately. The Rotunda takes no reservations. The Town's Tuck's Point facility page says it is "open to the public at all times," asks visitors not to block access to the docks while taking pictures, and doesn't allow tables or chairs on it.

The Chowder House is the space you can rent, and bookings for 2027 are already open. Residents could start reserving on October 15. Nonresident reservations open January 4, 2027. Resident rates are $325 Monday through Thursday and $400 Friday through Sunday. Nonresidents pay $750 and $900. Reservations are first come, first served. Forms are available at Town Hall and online, and payment is by cash or check only.

The facility page doesn't say how construction might affect 2027 rentals. Before booking a date in the summer of 2027, ask Town Hall how construction might affect that date. The Rotunda's target completion is early September, which falls after most of the summer rental calendar.

Where the Harbor's History Shows Up This Season

The work happens out on the water. On land, the town's fall calendar includes a talk on the geology under Cape Ann's coastline, along with the Museum's other programs.

  1. Fall Art Show, through November 14. The Manchester-by-the-Sea Museum's annual show of original work by local artists runs October 29 through November 14. The work is on display and for sale.
  2. Geology of Cape Ann, November 5. Richard Bedell speaks on the region's geology at First Parish Community Hall from 6 to 8 p.m. as part of the Museum's Fall Speaker Series.
  3. Nathaniel Philbrick, November 19. The author discusses his book The Rush at First Parish Church, Congregational. Doors open at 6 p.m. Details are on the Museum's event page.
  4. Holiday Stroll and Christmas-by-the-Sea, December 4. From 3 to 8 p.m., the Greater Cape Ann Chamber's Holiday Stroll and Business Open House brings refreshments to participating downtown shops. During the same hours, the Museum hosts its Christmas-by-the-Sea Open House at 10 Union Street.

For anything about the harbor work itself, the Special Town Meeting on November 16 at 7 p.m. at Memorial School is the next scheduled gathering of the town's legislative body.

The Town gives its own reason for the project in the March update. It wants residents to keep "catching crabs, posing for prom, or simply watching the boats come in and out of the harbor" at the Rotunda for generations to come. The Rotunda is scheduled to reopen in early September 2027 at the same spot, on steel pilings, five feet higher than it stands now.

On Manchester's waterfront, public projects like this one shape what a property is like to own. That includes the view from the porch, the tax bill, and when the harbor gets quiet. This post is general information. For how a debt exclusion or capital project affects your own tax situation, check with a qualified tax professional. If you'd like to talk through what Manchester's harbor projects mean for a home you own or are considering, Peggy Dowcett has been following them closely and is glad to help. Work With Peggy.

WORK WITH PEGGY

Peggy has lived in the area since 1992 and has enjoyed raising her family in the community. She brings her considerable attention to detail, commitment to our clients, broad network of connections, professional and technological skills.

Let's Connect

Follow Us on Instagram